Date, Fig and Jujube Drying Line | High-Sugar Fruit Dried Clean, Without Sugaring Out
Dates, figs and jujubes carry 55-70% sugar, and that sugar decides the drying recipe: dry them fast or hot and the skin hardens, sugar weeps to the surface and the batch turns sticky and dark. This line runs a brush wash, a wax-cracking dip, then staged 50-65°C heat pump drying to 18-24% moisture, followed by conditioning, grading and packing. Sized from 1 t/day for a cooperative to 10 t/day for an export packer.

A date drying line takes whole fruit through brush washing, wax-layer cracking, staged 50-65°C heat pump drying, conditioning and grading. Whole dates, figs and jujubes finish at 18-24% moisture for the soft-chew grade in 24-48 hours.
The critical control is sugar migration: sugar moves from the flesh to the surface when the skin stays intact and the temperature spikes early. Cracking the wax layer and holding a staged temperature curve keeps the sugar inside the fruit and the surface dry.
Indicative equipment budget: USD 18,000-45,000 for a 1-2 t/day room line, USD 45,000-90,000 for 3-5 t/day, USD 90,000-180,000 for 8-10 t/day with grading and packing. Equipment is typically only 35-55% of a landed project; freight, customs, civil works, installation and commissioning make up the rest.
From Fresh Fruit to Graded Packs, Stage By Stage
1. Intake and brush washing
Fruit is tipped into a receiving hopper and passed through a brush washing machine – for dates typically a brush washer with an ozone or spray rinse. The brushes strip dust and field residue from the wrinkled skin, which a spray bar alone cannot reach.
2. Wax-layer cracking
Dates and jujubes carry a thin wax layer that locks moisture in. A 30-60 second dip in 80-90°C water, or scoring by brush, micro-cracks the skin so moisture leaves evenly. Skip this step and drying time stretches while the skin case-hardens.
3. Staged heat pump drying – the core stage
Fruit is tray-loaded onto trolleys and dried in heat pump rooms on a staged curve: 50-55°C while free water leaves, rising to 60-65°C mid-cycle, then backing to 50-55°C to finish. Humidity is discharged, not recirculated, so the chamber stays below the point where surface sugar turns sticky.
4. Conditioning
Fruit leaves the room at uneven moisture between skin and flesh. Resting 12-24 hours in ventilated bins lets it equalise to a uniform 18-24%, so packs hold the soft-chew texture buyers grade by instead of sweating in the bag.
5. Grading and packing
Fruit is size-graded – by roller grader or manual inspection – then packed: 5-10 kg barrier cartons for bulk buyers, or retail bags from a packing machine. Metal detection sits before packing for export lots.
What The Line Contains – Wet End, Rooms and Downstream
| # | Equipment | Qty | Power | What it does |
|---|---|---|---|---|
| 1 | Receiving hopper and dates brush washing machine | 1 | 3-5.5 kW | Strips dust and residue from wrinkled skins before drying |
| 2 | Hot-water dip tank or steam conditioner | 1 set | 18-36 kW | 30-60 s at 80-90°C cracks the wax layer for even moisture loss |
| 3 | Heat pump drying rooms, 2-8 chambers | 1 set | 30-90 kW | Staged 50-65°C drying with humidity discharge |
| 4 | Trolleys and food-grade trays | per room | – | Single or double layer loading, 8-12 kg fruit per m² |
| 5 | Conditioning bins, ventilated | 2-4 | – | 12-24 h moisture equalising |
| 6 | Size grader (roller or manual table) | 1 | 1.5 kW | Jumbo, large, medium grades |
| 7 | Metal detector and packing machine | 1 set | 4.5-7.5 kW | Final safety check, barrier bags or retail packs |
Configuration shown for a 3-5 t/day fresh-fruit line. Typical arrangement – final equipment list and motor ratings are confirmed after a drying test with your fruit.
High-Sugar Fruit Handling, Built By Us



Tell Us Your Material And Capacity – We Size The Line
- Material, variety and initial moisture
- Fresh input per day or per hour
- Target final moisture and finished grade
- Available heat source and factory dimensions
Prefer email? Write to info@tondemachine.com or WhatsApp +86 185 0387 4173. Our engineers reply within one working day.
Why High-Sugar Fruit Needs One Supplier, Not Three
Every mistake in a date line compounds: a washer that splits skins feeds a dip tank that over-softens them, and fruit that enters the rooms wet sticks to trays within the first hour. When one engineering team supplies the washer, the dip, the rooms and the packer, the whole curve is tuned on the same fruit.
We build the brush washers, blanchers, drying rooms and packing machines in our own factory and quote them as one system sized to the same daily tonnage – one layout, one commissioning team, one spares catalogue.
That is what makes the sugar-migration control real: the dip temperature, the room recipe and the loading density were tested together, not assumed from three different manuals.
Rooms and Equipment



Three Capacity Tiers
| Parameter | Co-op line | Mid-size plant | Export plant | Data basis |
|---|---|---|---|---|
| Fresh fruit input | 1-2 t/day | 3-5 t/day | 8-10 t/day | B – industry |
| Water removed | 0.4-0.9 t/day | 1.2-2.1 t/day | 3.2-4.5 t/day | C – estimate |
| Dried output | 300-600 kg/day | 0.9-1.6 t/day | 2.4-3.3 t/day | C – estimate at 3-4:1 |
| Cycle time | 24-48 h per batch | 24-48 h | 24-48 h | B – industry |
| Drying rooms | 2-4 chambers | 4-8 chambers | 10+ chambers, staged loading | B |
| Installed power | 18-35 kW | 40-80 kW | 110-200 kW | C – estimate |
| Operators per shift | 3-4 | 5-8 | 10-15 | B – industry |
| Equipment budget | USD 18k-45k | USD 45k-90k | USD 90k-180k | B – indicative, ex-works |
Assumes whole fruit at 60-75% moisture dried to 18-24% for the soft-chew grade; a hard grade at 12-15% moisture raises the ratio to about 4-5:1. Figures marked C are typical, to be confirmed by test.
Send Your Material Data – Get a Line Layout & Price
- Daily or hourly fresh input and target final moisture
- Available heat source: electric, steam, gas, biomass or diesel
- Factory length, width and clear height
- Target market grade and packing format
Prefer email? Write to info@tondemachine.com or WhatsApp +86 185 0387 4173. Our engineers reply within one working day.
Power, Heat and Water
| Utility | Co-op line | Mid-size plant | Export plant | Data basis |
|---|---|---|---|---|
| Electricity | 18-35 kW installed | 40-80 kW | 110-200 kW | C – estimate |
| Hot water (wax-cracking dip) | 0.3-0.8 t/h at 85°C | 1.0-2.0 t/h | 2.5-4.0 t/h | C – estimate |
| Water (washing) | 2-4 m³/day | 5-10 m³/day | 12-20 m³/day | C – estimate |
| Energy per kg water removed | 0.5-0.8 kWh (heat pump) | 0.5-0.8 kWh | 0.5-0.8 kWh | C – typical, to be confirmed by test |
Heat pump drying suits high-sugar fruit because the curve is held, not chased: staged temperatures and humidity discharge are what keep the surface dry. Industry-typical figures, to be confirmed by test.
Floor Space and Building Requirements
| Item | Co-op line | Mid-size plant | Export plant |
|---|---|---|---|
| Room line footprint | 6×10 m | 10×18 m | 15×30 m plus packing hall |
| Clear height | 3.5-4 m | 4-4.5 m | 4.5-5 m |
| Layout | single row | single row | two rows around a trolley lane |
| Floor | washable, drained | food-grade, drained | food-grade, heavy point loads |
| Container count | 1 x 40HQ | 2-3 x 40HQ | 5-7 x 40HQ |
Wash water carries fruit sugar and needs settlement before disposal. Fruit fly and hygiene zoning matter for export packers – keep the wet end, rooms and packing hall separable.
How To Read The Numbers On This Page
About the numbers on this page. Capacity, temperature and moisture figures are industry-typical values for this material. Energy consumption, utility requirements, floor space and payback are engineering estimates and are marked typical, to be confirmed by test. We confirm every figure against a drying test with your own material before quotation. Price ranges are indicative ex-works figures and exclude freight, customs clearance, civil works, utilities, installation and commissioning – equipment typically accounts for 35–55% of a landed project budget.
Frequently Asked Questions
Why does sugar leak out of dates during drying?
Sugar migrates when moisture cannot leave through the skin fast enough: the wax layer holds water in, the chamber gets humid, and dissolved sugar moves to the surface and stays there. Cracking the wax layer and holding a staged temperature with humidity discharge keeps the surface dry and the sugar inside the flesh.
Is the hot-water dip needed for every variety?
Most wax-coated dates and jujubes benefit from a 30-60 second 80-90°C dip. Figs usually need a lighter treatment or none at all. We confirm the exact treatment on a drying test with your fruit before the layout is drawn.
What moisture should I target?
The soft-chew export grade finishes at 18-24% moisture; a hard, long-storage grade finishes at 12-15%. The line reaches either from the same rooms – what changes is cycle time and conditioning.
Can dates, figs and jujubes share the same rooms?
Yes, and most multi-crop packers do. The rooms are neutral; what changes is the recipe – loading density, dip treatment and the staged curve. Strong-aroma varieties are scheduled apart so flavours do not transfer.
How is this better than sun drying?
Sun drying takes 7-14 days, exposes open fruit to dust, insects and rain, and cannot hold a curve – which is exactly why surface sugaring is common in sun-dried lots. A controlled room finishes in 24-48 hours with the fruit closed inside insulated chambers.
Will you test my fruit before I commit?
Yes. Send 5-10 kg of each variety and we wash, dip and dry them on the quoted machine type, then return the drying curves, colour photos and moisture readings. The line is sized from those results.
The Dryers Used In This Line
Every line is built around one of these machines. Compare them, or send us your material and we will specify the right one.
Continuous Belt Food Drying Machine500-3,000+ kg/h, 1-5 layers, ambient to 120 degrees C, multi-zone PID control.View machine details →
Industrial Heat Pump Food Drying MachineClosed-loop batch drying rooms, saves 60-75% electricity, gentle 20-80 degrees C.View machine details →
Heat Pump Drying Room for ChiliPurpose-built chili drying room: staged recipes, high load per batch, low energy cost.View machine details →
Hot Air Circulation Drying Oven48-240 trays per batch, SUS304 body, up to 50% thermal efficiency.View machine details →
Double Door Hot Air Drying OvenCT-C batch oven: 60-480 kg per batch, 24-192 trays, steam or electric heating.View machine details →
Small Single Door Drying OvenCompact starter oven: 24 trays, 40-60 kg per batch, plug-and-play operation.View machine details →
Microwave Vegetable Drying MachineDries and sterilizes in minutes at 2450 MHz, 16-200 kg/h dehydration capacity.View machine details →
Food Freeze DryerVacuum sublimation keeps 97% of nutrients, color and aroma; 25-year shelf life.View machine details →Other Drying Lines In This Series
Industrial Chili Drying Line – 500 kg to 8 TonDehydrated Onion Production Line – Onion FlakeFood Drying Line Cost and Payback – Budget, RuGarlic dehydration lineMango drying lineMixed vegetable dehydration lineGinger & turmeric lineBanana & plantain lineMulti-product line (hub)Mushroom drying lineFish & seafood lineJerky & pet treats lineCassava & flour lineTomato & berry lineNon-fried crisps lineRoot vegetable dehydration lineCoffee, cocoa & nut lineHerb & spice lineTea leaf lineLayout & utilitiesTurnkey processPre-treatment linePost-treatment line
Request Your Turnkey Quotation
- Factory-direct price, no middleman
- Process design, layout drawing and utility specification
- Drying test with your own material before quotation
- Worldwide shipping, installation and remote commissioning support
Prefer email? Write to info@tondemachine.com or WhatsApp +86 185 0387 4173. Our engineers reply within one working day.